Bioenergy Call

On February 6, 2008, BC Hydro issued its Bioenergy Call. Detailed proponent requirements are found on BC Hydro's Bioenergy Call for Power website. BCTC facilitates BC Hydro's Competitive Electricity Acquisition Process by providing interconnection studies. The information from these studies will be used by BC Hydro to evaluate and select successful bidders.

What does an IPP need to do?

Under Phase I of this call, IPPs with transmission system connected projects must submit their application to BCTC.

The application is comprised of:

  • Submitting an Interconnection Request form (XLS, 602KB) by March 7, 2008
  • Signing a Feasibility Study Agreement by 4:00 pm PPT on April 7, 2008
  • Submitting a $30,000 deposit by 4:00 pm PPT on April 7, 2008

IPPs must resolve application deficiencies by April 7, 2008.

To proceed through the study process, IPPs will be required to meet technical requirements and provide data to BCTC in a timely manner. More details will be communicated to IPPs through workshops.

The complete Phase I schedule is available on BC Hydro's Bioenergy Call for Power website.

What does BCTC do?

Event/Activity Timeline
Review IR for completeness and work with IPP to resolve deficiencies April 7, 2008
Study individual IRs via the Feasibility Study April 8, 2008 to
June 19, 2008
Release Feasibility Study June 20, 2008 
Perform special studies for BC Hydro during its evaluation and selection process June 21, 2008 to
October 15, 2008 
Workshop for BC Hydro's selected IPPs After October 16, 2008

What does this process look like?

High level and detailed process charts will provide you with an overview of the CEAP process for the Bioenergy Call Phase I:

Resources

 

In this section: