| Commence Public/First Nations Consultation on Alternatives |
Summer 2006 |
| Initiate EA Process for new Transmission Line Alternative |
December 2006 |
| Commence Environmental Studies |
March 2007 |
| BCTC Decision on Recommended Alternative |
May 2007 |
| File Application with BC Utilities Commission |
Fall 2007 |
| Anticipated BCUC Decision |
Fall 2008 |
| File Environmental Assessment Application |
Fall 2008 |
| Anticipated Environmental Approval |
Summer 2009 |
| Construction Period |
Fall 2009-2014 |
| Anticipated In-service date |
Fall 2014 |