Project Schedule

This schedule is subject to change.

Milestone Date (subject to change)
Commence Public/First Nations Consultation on Alternatives Summer 2006
Initiate EA Process for new Transmission Line Alternative December 2006
Commence Environmental Studies March 2007
BCTC Decision on Recommended Alternative May 2007
File Application with BC Utilities Commission Fall 2007
BCUC Decision August 2008
Environmental Assessment Application accepted for formal review November 2008
Environmental Assessment Certificate Issued June 2009
Anticipated In-service date Fall 2014