Schedule

This schedule is subject to change.

Milestone Date (subject to change)
Commence Public/First Nations Consultation on Alternatives Summer 2006
Initiate EA Process for new Transmission Line Alternative December 2006
Commence Environmental Studies March 2007
BCTC Decision on Recommended Alternative May 2007
File Application with BC Utilities Commission Fall 2007
Anticipated BCUC Decision Fall 2008
File Environmental Assessment Application Fall 2008
Anticipated Environmental Approval Summer 2009
Construction Period Fall 2009-2014
Anticipated In-service date Fall 2014